Activity-Based Costing and Bidding on Jobs Vance Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. The company's estimator has been
Activity-Based Costing and Bidding on Jobs
Vance Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. The company's estimator has been involved in a long-simmering dispute with the on-site work supervisors. The on-site supervisors claim that the estimator does not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and non-routine work such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that non-routine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: "My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square metres by $4,000 per thousand square metres to determine the bid price. Since our average cost is only $3,000 per thousand square metres, that leaves enough cushion to take care of the additional costs of non-routine work that shows up. Besides, it is difficult to know what is routine or not routine until you actually start tearing things apart."
To shed light on this controversy, the company initiated an activity-based costing study of all of its costs. Data from the activity-based costing system follow:
Activity Cost PoolActivity MeasureTotal Activity
Removing asbestosThousands of square metres500,000 m2
Estimating and job setup Number of jobs200 jobs*
Working on non-routine jobsNumber of non-routine jobs25 non-routine jobs
Other (costs of idle capacity and
organization-sustaining costs) Not applicable; these costs are
not allocated to jobs
*The total number of jobs includes non-routine jobs as well as routine jobs. Non-routine jobs as well as routine jobs require estimating and setup work.
Wages and salaries$200,000
Disposal fees 600,000
Equipment depreciation 80,000
On-site supplies60,000
Office expenses 190,000
Licensing and insurance 370,000
Total cost$1,500,000
Distribution of Resource Consumption
across Activity Cost Pools
Estimating Working on
Removing and JobNon-routine
Asbestos SetupJobsOther Total
Wages and salaries40%10%35%15%100%
Disposal fees 70%0%30%0%100%
Equipment depreciation50%0%40%10%100%
On-site supplies55%15%20%10%100%
Office expenses10%40%30%20%100%
Licensing and insurance50%0%40%10%100%
Required: I HAVE COMPLETED Q. 1 and 2, PLEASE FOCUS ON 3 AND 4:
1.Perform the first-stage allocation of costs to the activity cost pools.
2.Compute the activity rates for the activity cost pools.
3.Using the activity rates you have computed, determine the total cost and the average cost per thousand square metres of each of the following jobs according to the activity-based costing system.
a.A routine 2,000-square-metre asbestos removal job.
b.A routine 4,000-square-metre asbestos removal job.
c.A non-routine 2,000-square-metre asbestos removal job.
4.Given the results you obtained in (3) above, do you agree with the estimator that the company's present policy for bidding on jobs is adequate?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started