ActivityPredecessorOptimisticMost LikelyPessimistic A- 1515 15 B- 4045 60 C- 1014 30 D- 22 5 EA 57 9 FB,C,D,E 45 8 GF 11 1 HG 2530
ActivityPredecessorOptimisticMost LikelyPessimistic
A- 1515 15
B- 4045 60
C- 1014 30
D- 22 5
EA 57 9
FB,C,D,E 45 8
GF 11 1
HG 2530 50
IH 35 10
JI 33 10
KI 2030 45
LI 33 5
MJ,K,L 33 3
NM 1013 20
OM 1014 28
PN,O 22 2
QP 55 5
Analyze the probability of completing this work in 150 weeks using PERT ( z score)