Actual fixed overhead is $350 000, while budgeted fixed overhead is $299 000. What is the fixed overhead static-budget variance if 250 000 units are
Actual fixed overhead is $350 000, while budgeted fixed overhead is $299 000. What is the fixed overhead static-budget variance if 250 000 units are produced and 225 000 are budgeted?
Select one:
1.$50 000 favourable
2.$50 000 unfavourable
3.$51 000 favourable
4.$51 000 unfavourable
5.none of the above