Question

1 Approved Answer

Actual run time this week ? minutes Machine time available this week 5,000 minutes Actual run rate this week ? units per minute Ideal run

Actual run time this week ? minutes
Machine time available this week 5,000 minutes
Actual run rate this week ? units per minute
Ideal run rate 4.0 units per minute
Defect-free output this week 15,000 units
Total output this week (including defects) ? units

If the quality rate is 0.80, then the total number of units lost due to the combined utilization, efficiency, and quality losses is closest to:

Multiple Choice

  • 2,000 units

  • 1,250 units

  • 1,500 units

  • 1,750 units

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Debates On Politics And Public Administration In The Postmodern Era

Authors: Ă–mer Ugur, Kadir Caner Dogan

1st Edition

3631796331, 9783631796337

More Books

Students also viewed these Accounting questions

Question

understand the limitations of classic models of job design.

Answered: 1 week ago

Question

Solve the integral:

Answered: 1 week ago

Question

What is meant by Non-programmed decision?

Answered: 1 week ago

Question

What are the different techniques used in decision making?

Answered: 1 week ago