Ad team is a semester - long project. Interested students need meeting where the various tasks in the team project are allotted. A group researches

Ad team is a semester-long project. Interested students need meeting where the various tasks in the team project are allotted. A group researches competin products. Another group designs a survey to research customer demand; results of the survey then analyzed. After the research is done, an advertising campaign is created. Those students who will be presenting have to rehearse while the rest of the students give constructive feedb on their performance. Last of all is the presentation to a panel of judges. All these activities h to be done in the following order:
\table[[Activities,Immediate Predecessors,Time (weeks)],[A. Register,-,3],[B. Meeting,A,1],[C. Research competition,B,3],[D. Survey,B,2],[E. Analysis,D,2],[F. Create ad campaign,C,E,4],[G. Rehearse,F,2],[H. Presentation,G,1]]
a) Draw a project (PERT/CPM) network for the ad team project.
b) Compute Early Start and Early Finish times for the activities in the project.
c) Compute Late Finish and Late Start times for the activities in the project.
d) Find the activities on the critical path.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ecological Forest Management

Authors: Jerry F. Franklin, K. Norman Johnson, Debora L. Johnson

1st Edition

1478633506, 978-1478633501

More Books

Students also viewed these General Management questions