Additional Algo 19-2 Early Finish Time The network diagram and task times for a project are shown below. The process is as follows:A 1 to
Additional Algo 19-2 Early Finish Time
The network diagram and task times for a project are shown below.
The process is as follows:A 1 to A 2 and A 3. A 2 and A 3 to A 4 then A 5.
Task | Duration (days) |
---|---|
A1 | 2 |
A2 | 2 |
A3 | 7 |
A4 | 1 |
A5 | 7 |
What is the early finish time for activity A5 ?