Question
ADJUSTING COST OF CAPITAL FOR RISK Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk
ADJUSTING COST OF CAPITAL FOR RISK
Ziege Systems is considering the following independent projects for the coming year:
Project | Required Investment | Rate of Return | Risk |
A | $4 million | 13% | High |
B | 5 million | 10.5 | High |
C | 3 million | 8.5 | Low |
D | 2 million | 8.5 | Average |
E | 6 million | 11.5 | High |
F | 5 million | 11.5 | Average |
G | 6 million | 6.5 | Low |
H | 3 million | 10.5 | Low |
Ziege's WACC is 9.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2% for low-risk projects.
a. Which projects should Ziege accept if it faces no capital constraints?
b. If Ziege can only invest a total of $13 million, which projects should it accept?
If Ziege can only invest a total of $13 million, what would be the dollar size of its capital budget? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
$---- million
c. Suppose Ziege can raise additional funds beyond the $13 million, but each new increment (or partial increment) of $5 million of new capital will cause the WACC to increase by 1%. Assuming that Ziege uses the same method of risk adjustment, which projects should it now accept?
d. What would be the dollar size of its capital budget? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
$ ---million
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started