Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the

Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the companys five activity cost pools:

Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity
Labor-related Direct labor-hours $ 40,000 5,000 DLHs
Purchase orders Number of orders $ 6,400 3,200 orders
Material receipts Number of receipts $ 11,700 900 receipts
Relay assembly Number of relays $ 24,200 2,200 relays
General factory Machine-hours $ 380,000 38,000 MHs

2. The expected activity for the year was distributed among the companys four products as follows:

Expected Activity
Activity Cost Pool Product A Product B Product C Product D
Labor-related (DLHs) 2,250 550 1,750 450
Purchase orders (orders) 350 700 800 1,350
Materials receipts (receipts) 600 111 189 0
Relay assembly (relays) 310 310 330 1,250
General factory (MHs) 15,500 4,200 3,800 14,500

Using the ABC data, determine the total amount of overhead cost assigned to each product.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Personal Finance

Authors: Jeff Madura, Hardeep Singh Gill

4th Canadian edition

978-0134724713

Students also viewed these Accounting questions