Question

1 Approved Answer

After 3 months, the progress of a project is reported as follows: Planned Completed Work 20% Actual Completed Work 10% Budget Spent so far 300,000

After 3 months, the progress of a project is reported as follows:

Planned Completed Work 20%
Actual Completed Work 10%
Budget Spent so far 300,000
Total Budget 1,000,000

Please answer the following questions (a to m) and please show your work to get full credit.

a. What is the Budget at Completion (BAC)? )

b. What is the Earned Value (EV)?

c. What is the Planned Value (PV)?

d. What is the Actual Cost (AC)?

e. What is the Cost Variance (CV)?

f. What is the Schedule Variance (SV)?

g. What is the Cost Performance Index (CPI)?

h. What is the Schedule Performance Index (SPI)?

i. What is the Estimation at Completion (EAC)?

j. What is the Estimation to Completion (ETC)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management And The Arts

Authors: William J. Byrnes

5th Edition

0415663296, 978-0415663298

More Books

Students also viewed these General Management questions

Question

What leadership actions, if any, should team members take?

Answered: 1 week ago

Question

consider how quantitative data can contribute to your research;

Answered: 1 week ago

Question

draw appropriate conclusions based on your data.

Answered: 1 week ago

Question

make sense of basic terminology used in quantitative data analysis;

Answered: 1 week ago