After estimating a projects NPV, the analyst is advised that the fixed capital outlay will be revised upward by $73200. The fixed capital outlay is
After estimating a projects NPV, the analyst is advised that the fixed capital outlay will be revised upward by $73200. The fixed capital outlay is depreciated straight-line over a 6-year life. The tax rate is 40 percent, and the required rate of return is 9 percent. No changes in cash operating revenues, cash operating expenses, or salvage value are expected. What is the effect on the project NPV?