Question

1 Approved Answer

After3 months, the progress ofa project is reported as follows: Planned Completed Work 20% Actual Completed Work 10% Budget Spent so far 300,000 Total Budget

image text in transcribed
image text in transcribed
After3 months, the progress ofa project is reported as follows: Planned Completed Work 20% Actual Completed Work 10% Budget Spent so far 300,000 Total Budget 1.000.000 Please answerthe following questions (a to m) and please show your work to get full credit. a. What is the Budget at Completion {BAC}? ('I point} 1:). What is the Earned Value (EV)? [2 points] c. What is the Planned Value {PV}? (2 points] (I. What is the Actual Cost {AC}? [1 point) e. What is the Cost Variance {CV}? [2 points) f. What is the Schedule Variance {SV}? {2 points} g. What is the Cost Performance Index [CPI]? [2 points) h. What is the Schedule Performance Index (SPII? (2 points) i. What is the Estimation at Completion {EAC}? [2 points) j. What is the Estimation to Completion {ETC}?(2 points) k. What is Remaining Work based on BAC? (2 points] I. What is remaining Funds based on BAC? [2 points} m. What is the ToComplete Performance Index to meet the current EAC? (4 points]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring The Hospitality Industry

Authors: John R Walker

4th Edition

0134744934, 9780134744933

More Books

Students also viewed these General Management questions