Answered step by step
Verified Expert Solution
Question
1 Approved Answer
After3 months, the progress ofa project is reported as follows: Planned Completed Work 20% Actual Completed Work 10% Budget Spent so far 300,000 Total Budget
After3 months, the progress ofa project is reported as follows: Planned Completed Work 20% Actual Completed Work 10% Budget Spent so far 300,000 Total Budget 1.000.000 Please answerthe following questions (a to m) and please show your work to get full credit. a. What is the Budget at Completion {BAC}? ('I point} 1:). What is the Earned Value (EV)? [2 points] c. What is the Planned Value {PV}? (2 points] (I. What is the Actual Cost {AC}? [1 point) e. What is the Cost Variance {CV}? [2 points) f. What is the Schedule Variance {SV}? {2 points} g. What is the Cost Performance Index [CPI]? [2 points) h. What is the Schedule Performance Index (SPII? (2 points) i. What is the Estimation at Completion {EAC}? [2 points) j. What is the Estimation to Completion {ETC}?(2 points) k. What is Remaining Work based on BAC? (2 points] I. What is remaining Funds based on BAC? [2 points} m. What is the ToComplete Performance Index to meet the current EAC? (4 points]
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started