Question
AG is in the process of reviewing 10 proposals for new project, but the resources only available to work on new project for maximum 46200,
AG is in the process of reviewing 10 proposals for new project, but the resources only available to work on new project for maximum 46200, hours during the year. The incremental profit and constrained resource required for the proposed project are listed below:
Proposed Project Incremental Profit Amount of the Constrained Resource Required
Project 1 7.700.000 8.800
Project 2 5.500.000 11.000
Project 3 825.000 6.600
Project 4 4.950.000 6.600
Project 5 3.300.000 13.200
Project 6 2.750.000 4.400
Project 7 2.200.000 2.200
Project 8 660.000 4.400
Project 9 1.650.000 4.400
Project 10 880.000 4.400
30.415.000 66.000
Required:
a) Which of the proposed project should the company accept this year?
b) What would be the total incremental profit under your plan?
c) What is your opinion, why company's revenues and costs differ across customer?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started