Question
Aggregate Plan Assignment K. Cunningham Furniture products needs to develop its aggregate schedule for sofa production. The cost accounting department has supplied the costs relevant
Aggregate Plan Assignment
K. Cunningham Furniture products needs to develop its aggregate schedule for sofa production. The cost accounting department has supplied the costs relevant to the aggregate plan and the marketing department has provided a four-quarter forecast. All are shown below.
Quarter | Forecast |
1 | 1,400 |
2 | 1,200 |
3 | 1,500 |
4 | 1,300 |
Costs | |
Beginning inventory | 0 |
Stock-out cost for backorders | $50 |
Inventory holding cost | $10 per unit held at the end of the quarter |
Hiring workers | $400 per worker |
Firing workers | $550 per worker |
Unit material cost | $50 |
Regular wage rate | $30 |
Overtime wage rate | $45 |
Regular labor hours | 8 hours per day 25 days per month |
Maximum overtime labor hours | 100 hours per worker per quarter |
Labor hours required | 5 hours per unit |
Previous quarter demand | 1500 |
Previous quarter output | 1350 |
Subcontracting cost | $250 |
Current workforce | 25 employees |
Worksheet 1--Plan A: Develop a level plan that holds employment steady. Beginning workforce is 25. No subcontracting is allowed. Assume stock-outs at the end of the 4th quarter are no greater than 100 units. If you hold employment steady is the result a level plan? Why/why not? If it is not a level plan, how do you recommend moving toward a level plan? Comment on the constraints used. Answer the questions and comment in a text box on this worksheet.
Worksheet 2--Plan B: Develop a chase plan by hiring and firing as necessary to hold down costs. Assume the stock-outs at the end of the 4th quarter are no greater than 100 units. No overtime or subcontracting is allowed. Using a textbox on this worksheet, comment on the constraints used and the viability of the plan.Im not sure if I'm setting this up correctly
Decision Variables Number Hired, H Number Laid Off, Overtime Hours, o Ending Inventory, Backlogged Units, S. Subcontract Units, Focast Production Units, P, lo 0 lo 0 0 lo 0 JO 10 10 1400 1200 1500 1300 Costs 0 0 0 0 10 10 0 -SUM(G37:G48)*B9 JO 10 0 =SUM(E37:E40)* B15 0 JO JO 0 -SUM(F37:F40)*B10 10 lo 0 =SUM(H37:140)*B21 =SUM(C37:C40)*B11 -SUM(D37:040)*B11 jo -SUM(137:140)*813 Constraints 32 33 34 35 Quarter 36 37 1 38 2 39 3 40 4 41 42 43 44 45 Quarter 46 47 1 48 2 49 3 50 4 51 52 53 54 55 56 Production Overtime Limit Inventory Balance Capacity Workforce Size, w 1125 -B4B+C37-D37 -B474C-38-D38 -B484C39-039 B49+C40-D40 |ESUM(B47:650)*B25 -B47"WREFIE38WREF! -B48 MREFI4E39WREF! -B49 MREF4E4OREF! -B50'MREFI+MREFWREF! -B47*#REF! -B48*#REF! =B49*#REF! -B50*#REF! #REFI+F38 #REFI-HREF! #REF!4F394#REF!-B38-# =#REF!4F40+#REF!-B40- #REF! #REF! #REFI-#RE Decision Variables Number Hired, H Number Laid Off, Overtime Hours, o Ending Inventory, Backlogged Units, S. Subcontract Units, Focast Production Units, P, lo 0 lo 0 0 lo 0 JO 10 10 1400 1200 1500 1300 Costs 0 0 0 0 10 10 0 -SUM(G37:G48)*B9 JO 10 0 =SUM(E37:E40)* B15 0 JO JO 0 -SUM(F37:F40)*B10 10 lo 0 =SUM(H37:140)*B21 =SUM(C37:C40)*B11 -SUM(D37:040)*B11 jo -SUM(137:140)*813 Constraints 32 33 34 35 Quarter 36 37 1 38 2 39 3 40 4 41 42 43 44 45 Quarter 46 47 1 48 2 49 3 50 4 51 52 53 54 55 56 Production Overtime Limit Inventory Balance Capacity Workforce Size, w 1125 -B4B+C37-D37 -B474C-38-D38 -B484C39-039 B49+C40-D40 |ESUM(B47:650)*B25 -B47"WREFIE38WREF! -B48 MREFI4E39WREF! -B49 MREF4E4OREF! -B50'MREFI+MREFWREF! -B47*#REF! -B48*#REF! =B49*#REF! -B50*#REF! #REFI+F38 #REFI-HREF! #REF!4F394#REF!-B38-# =#REF!4F40+#REF!-B40- #REF! #REF! #REFI-#REStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started