Alan commenced business on 1 May 20X1, having obtained three orders for house extensions, the costs of which during his first months trading were as
Alan commenced business on 1 May 20X1, having obtained three orders for house extensions, the costs of which during his first months trading were as follows:
Job 1 Job 2 Job 3 $$$
Direct wages at $1.10 per hour. 528 451 308
Materials issued from stores. 2,752 2,341 1,473
Special materials bought in. 215. - 46
Materials returned to stores. 71. - -
Alan has estimated his overheads for the year ending 30 April 20X2 at $10,500 and the direct labour hours at 17,500. For costing purposes, overheads are absorbed on a direct labour hour basis. The actual overhead incurred in May was $800.
Job 1 was completed on 31 May and invoiced to the customer at the contracted price of $4,500.
Required:
-
(a) Calculate the total cost and profit of Job 1
-
(b) Calculate the total cost of Job 2 and Job 3
Direct labor unit not given
Step by Step Solution
There are 3 Steps involved in it
Step: 1
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started