Question
Albert Construction Company had a contract starting April 2018, to construct a $42,000,000 building that is expected to be completed September 2019, at an estimated
Albert Construction Company had a contract starting April 2018, to construct a $42,000,000 building that is expected to be completed September 2019, at an estimated cost of 38,500,000. At the end of 2018, the cost to date were $17,710,000 and the estimated cost to complete had not changed. The progress billings during 2018 were $8,400,000 and the cash collected during 2018 was $5,600,000/ Albert uses the percentage-of-completion method.
At December 31, 2018, Albert would report Construction in Process in the amount of ?
a) 19,320,000
b) 17,710,000
c) 16,520,000
d) 1,610,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started