Question
Alex is a project manager that is currently managing the construction of a hospital in Ethiopia. His Senior Project Manager, to whom he reports to,
Alex is a project manager that is currently managing the construction of a hospital in Ethiopia. His Senior Project Manager, to whom he reports to, sits in London, United Kingdom. Each week Alex is required to submit electronic reports to his Senior Project Manager, regarding the performance of the project. In addition to this, the Senior Project Manager also has access to the Project Dashboard created by Alex, through which, real time project information can be viewed. The main concerns in establishing this means of communication was to ensure the security and consistency of the transmission of information to the Senior Project Manager. This factor of communications is a concern of
a.
The managing and monitoring communications process, but the guidelines are included in the lessons learned document
b.
The managing communications process, but the guidelines are included in the communications management plan
c.
The managing communications process, but the guidelines are included in the managing communications document
d.
The monitoring communications process, but the guidelines are included in the communication management plan
e.
The monitoring communications process, but the guidelines are included in the monitoring communications document
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started