Alfa Ltd. enters into a 3 years contract, the costs and profit/loss details of which are: Contract price $30 m Estimated costs $21 m (when

Alfa Ltd. enters into a 3 years contract, the costs and profit/loss details of which are:
Contract price $30 m
Estimated costs $21 m (when the contract was signed)
Estimated profit: $9 m
Details of the actual costs and estimated costs to complete the contract are:
Year ended 31 March
Year 1
($000)
Year 2
($000)
Year 3 ($000)
Construction costs in the year
2 940
16 635
12 000
Costs to date
2 940
19 575
31 575
Estimated costs to complete
18 060
12 000
--
Estimated total costs (costs to date + costs to complete)
21 000
31 575
31 575
Notes:
- At the end of year 1 the project is still profitable and profit can be recognised.
- At the end of year 2 the projects total costs exceed the contract price. There will be an overall loss on the contract which must be recognised in year 2.
Required:
Prepare the general ledger for construction in process/progress (CIP) account.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions