Ali is an engineer who was recently assigned as a project manager to build a private villa. He has developed the below table. Code Activities
Ali is an engineer who was recently assigned as a project manager to build a private villa. He has developed the below table.
Code | Activities | Duration Days | Predecessors |
A | Draw a draft for the villa design | 5 | No predecessor |
B | Obtain the owners' approval | 3 | A |
C | Assign the contractor | 7 | B |
D | Assign the interior designer | 4 | B |
E | Finalize the contract | 5 | D and C |
Kindly assist Ali to do the following:
- Draw a Network Diagram
- Find the Critical Path
- Find the Early Start and Early Finish
- Find the Late Start and Late finish
- Find the float
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started