Alicia Spurell's expected return on a project is 8%. The company has a standard deviation of 21.4% on the project. What is the coefficient of

Alicia Spurell's expected return on a project is 8%. The company has a standard deviation of 21.4% on the project. What is the coefficient of variation of the project ?
A. 2.07
B. 0.275
C. 0.373
D. 2.68
E. 3.61