All of the following can be said about network diagrams EXCEPT: 1.For making a network diagram, a horizontal bar is drawn for each activity to

All of the following can be said about network diagrams EXCEPT:

1.For making a network diagram, a horizontal bar is drawn for each activity to show its sequence and duration. In a critical path, the order and duration of the sequence of activities directly affect the completion date of a project.

2.A sequence of connected activities that produce the longest overall time period is referred to as critical path.

3.The latest expected completion time refers to the time in which an activity can be completed without delayingtheproject.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Anger Management Workbook For Moms

Authors: Lena Suarez Angelino

1st Edition

1638074755, 978-1638074755

More Books

Students also viewed these General Management questions