Alpha Inc. has the following two projects that it is considering, and it wants to choose one. Project A has an investment outlay/expense today of
Alpha Inc. has the following two projects that it is considering, and it wants to choose one. Project A has an investment outlay/expense today of $1,040, and its cash flows over the next three years are $510, $610, and $750. Project B has an outlay of $2,080, and cash flows of $970, $1,290, and $1,480. Which project should Alpha choose? (You can assume no taxes.)