Question
American Constructors Inc.: World Outreach Expansion Project. PART 2 4. Crash the project in order to be finished by the required date: a) A certain
American Constructors Inc.: World Outreach Expansion Project.
PART 2 4. Crash the project in order to be finished by the required date:
a) A certain degree of crashing will be possible with info in the case, but if that is not enough you may use other means such as overtime, additional resources, etc. Also, use your understanding of business and human nature. Type and submit rationale for each crashing decision in a MS Word file.
b) ONLY crash lowest level tasks, allowing the supervisory tasks to be crashed only because the tasks beneath them are crashed.
c) You need to have at least one instance of working on the weekend and at least one instance of working overtime during the week - include all of these with your rationale for crashing.
d) You may crash the Lobby construction task (include rationale), but only down to the minimum indicated in the case.
Working with calendars: - There is a Project Calendar and also a Calendar for each Work resource. The default is five 8-hour days with no work occurring on weekends. - To change working times: Project - Change Working Time, choose the Calendar for the Resource, click on day you want to add, Exceptions tab - type name of exception, Details - click on Working Times... - You can do many things with these calendars - two examples are given below: - If there is a day most people will not be working (e.g. Saturday), but you want to have a few resources working on that day, you must set "Nondefault working time" for each of the resources that are to be working. - If you want everyone in the whole project to not do anything for a period of time, can use the Project Calendar to set "Nonworking times" even during regular working hours
5. Resource Allocations: a. First: If a resource is consistently available only a portion of the time for this project, reduce the Max. Units on the Resource Sheet. b. Level the project by fixing any resource over-allocations
Look at the Resource Usage Sheet to see which resources are overallocated on which days.
First, for the human resources on the lowest level tasks, fix remaining issues regarding a person being assigned to do two tasks at the same time. If it makes sense in the case, add precedence relationships that fix this. (We are changing from a technically-constrained to resource-constrained plan, just for lower level activities)
Then to complete the leveling, reduce the percentage allocation on the Gantt Chart (double click on task, Resources tab) OR manually change the hours worked on each task in the Resource Usage View.
If are having difficulty, as a last resort you may use lags and task splitting - but only if that makes sense for the task.
6. Input reasonable cost estimates for all resources
a) Consider which costs would be tracked as hourly wages (Although some of the work resources would be on salary, enter the equivalent hourly rate - this is to track for accounting purposes). Also consider which costs would be charged by piece, which would likely be done by a fixed-price contract, and which may have no monetary cost.
b) The case does not have individual costs reported, so you will have to make up "reasonable" costs for all items. For grading, I will only consider whether a cost is "in the ballpark" - so as long as they aren't completely ridiculous it will be fine. Consider the total remaining cost and have your costs add up approximately to that: it is logical to assume that construction started approximately 18 months before Sept 2009, so the remaining total cost for the last 3 months is only part of the $34M. So if the whole project is going to take 18mo+3mo = 21 months, one estimate of the remaining total cost is 3/21 * $34M = $4.85M, or approximately $5M remaining
c) Tom Grott must be given an hourly wage - we don't know how much he makes on salary, but put in $50/hour (for accounting purposes, project wages are often calculated by the hour even for salaried employees).
d) Do NOT use fixed task costs (the way we assign costs to a Cost Resource is by task, but it only applies to the resource - not the whole task)
e) Do not put in any overtime wages - we assume people are on salary or paid by the hour, and MS Project doesn't handle OT intuitively.
f) Important: Double-check that you have entered costs properly by: from the Gantt chart Entry view, View - Tables - Cost and manually check Work, Material and Cost cost totals for a few specific tasks - be sure to understand where every dollar in this view comes from for a few tasks 7. The project plan is now complete - you are ready to start implementing the project. Therefore, save the baseline (and show the baseline by switching to Tracking Gantt View) Note: Since the baseline has just been saved, the Variance column in View-Tables-Cost should have only zeros in it.
8. Choose a task that has a material resource with a cost and a work resource with an hourly cost.
9. Pretend you are actually implementing the project by setting lowest level activities that occur earlier than the end of the task chosen in step 8 as 100% complete, including 100% for the task chosen in #8. Then consider if there are other parallel tasks/paths that would probably be partially completed by that date (i.e., the end of the task chosen in step 8) and set those to be partially complete so that all paths are close to being on schedule at this date.
ONLY do this for the lowest level tasks, do not implement supervisory tasks because they will be implemented automatically as the ones beneath them are. After doing this, Check 'Gantt Chart, View - Tables - Cost' and 'Gantt Chart, View - Tables - Variance' to ensure ALL variance values are still zero
10. Input a project delay & cost over-run:
For the task chosen in step 8, input it as taking longer than expected - so add some time (in the duration column). Add enough time that the project is past at least one of your deadlines. (Choose the correct drop-down option so that the task actually takes more work than before.) If the above change causes overallocation for any resources, that is fine. Also, for the same task, increase the quantity required for the material resource by changing it on the Gantt Chart, View-Table-Entry
Go to 'Tracking Gantt, View - Tables - Cost'. For every non-zero value in the entire variance column, explain why there is variance. Show the math - TYPE this to hand in. There is an example of this on the last page of these instructions.
Task Name | Duration | Start | Finish | Predecessors | Successors | Resource Names |
American Constructors Inc.: World Outreach Expansion Project Goals and Objectives | 81 days? | Thu 9/24/09 | Thu 1/14/10 | |||
Receive close-out documents from architect | 15 days | Thu 9/24/09 | Wed 10/14/09 | 46 | Tom Grott | |
Meetings with Team, Architect & Client | 1 day | Thu 9/24/09 | Thu 9/24/09 | 6,20,22,37,17 | Tom Grott,Archiects [25%] | |
Church Construction | 80 days? | Fri 9/25/09 | Thu 1/14/10 | |||
Store/Kitchen/Caf | 69 days | Fri 9/25/09 | Wed 12/30/09 | 45 | ||
Contrustruction Task | 69 days | Fri 9/25/09 | Wed 12/30/09 | |||
Drywall | 23 days | Fri 9/25/09 | Tue 10/27/09 | 2 | 7,8,9 | Cage Drywall,Drywall Materials [1 sheets] |
Hard tile | 10 days | Wed 10/28/09 | Tue 11/10/09 | 6 | 12 | ACI crew |
Stone Column | 5 days | Wed 10/28/09 | Tue 11/3/09 | 6 | 12 | ACI crew,Natural Stone Materials [5 tons] |
Millwork | 21 days | Wed 10/28/09 | Wed 11/25/09 | 6 | 10 | Intergrity Architectural Millwork |
Casework | 5 days | Thu 11/26/09 | Wed 12/2/09 | 9 | 11 | ACI crew |
Flooring Installation | 10 days | Thu 12/3/09 | Wed 12/16/09 | 10 | 14,15 | ACI crew |
Glass Installation | 3 days | Wed 11/11/09 | Fri 11/13/09 | 7,8 | 13 | Glass Materials [1,000 square feet],ACI crew |
Painting | 10 days | Mon 11/16/09 | Fri 11/27/09 | 12 | 14,15 | Charlie Irwin Painting |
Doors and Hardware Installation | 8 days | Thu 12/17/09 | Mon 12/28/09 | 11,13 | 45,16 | Carpenters,Doors Materials[50 units] |
M.E.P | 10 days | Thu 12/17/09 | Wed 12/30/09 | 11,13 | 45 | Roscoe Brown,S&W Electric |
Store/ Kitchen/Caf Setup completed | 0 days | Mon 12/28/09 | Mon 12/28/09 | 14 | ||
Lobby Construction | 62 days | Fri 9/25/09 | Mon 12/21/09 | 2 | 45 | Bridget Brodbeck ,Subcontactor,Tom Grott,Cage Drywall,ACoustical Ceiling Tile,Larry Hawker |
Sanctuary | 62 days | Fri 9/25/09 | Mon 12/21/09 | |||
Own Crew / Subcontactor | 62 days | Fri 9/25/09 | Mon 12/21/09 | |||
Hanging & finishing drywall | 16 days | Fri 9/25/09 | Fri 10/16/09 | 2 | 30 | Cage Drywall |
Audiorium seating | 62 days | Fri 9/25/09 | Mon 12/21/09 | |||
Core drill for the rails | 2 days | Fri 9/25/09 | Mon 9/28/09 | 2 | 25,26,31 | ACI crew |
Carpating at the Rails | 5 days | Tue 11/24/09 | Mon 11/30/09 | 25,24 | 45 | ACI crew |
Wood Panelling, trim and stage work | 25 days | Tue 10/20/09 | Mon 11/23/09 | 26 | 34,23,28 | Intergrity Architectural Millwork,Wood Materials [500 cubic feet] |
Rails installing | 15 days | Tue 9/29/09 | Mon 10/19/09 | 22 | 23 | |
Carpeting seats | 15 days | Tue 9/29/09 | Mon 10/19/09 | 22 | 27,24 | ACI crew |
Painting | 20 days | Tue 10/20/09 | Mon 11/16/09 | 32,26 | 34 | Charlie Irwin Painting |
Seat at Audi | 20 days | Tue 11/24/09 | Mon 12/21/09 | 39,24 | 35,45 | ACI crew |
The bowl | 60 days | Tue 9/29/09 | Mon 12/21/09 | |||
Installing seats | 20 days | Mon 10/19/09 | Fri 11/13/09 | 20 | 35 | ACI crew |
Wood stage step | 5 days | Tue 9/29/09 | Mon 10/5/09 | 22 | 32,33 | ACI crew |
Stain floor | 5 days | Tue 10/6/09 | Mon 10/12/09 | 31 | 27 | ACI crew,Stained concrete Materials [15 cubic yards] |
Carpeting at Bowl | 5 days | Tue 10/6/09 | Mon 10/12/09 | 31 | Commercial carpeting subcontractor | |
Doors installation and matching handware | 8 days | Tue 11/24/09 | Thu 12/3/09 | 24,27 | 35,45 | Carpenters |
Santuary Setup Complete | 0 days | Mon 12/21/09 | Mon 12/21/09 | 34,28,30 | 45 | |
The terrace | 46 days | Fri 9/25/09 | Fri 11/27/09 | |||
Window installation | 8 days | Fri 9/25/09 | Tue 10/6/09 | 2 | 38 | ACI crew,Windows Materials[30 units] |
Waterproofing | 7 days | Wed 10/7/09 | Thu 10/15/09 | 37 | 39 | ACI crew |
Insulation | 3 days | Fri 10/16/09 | Tue 10/20/09 | 38 | 28,40 | ACI crew |
Deck completion | 8 days | Wed 10/21/09 | Fri 10/30/09 | 39 | 41,42 | ACI crew |
Stairs | 10 days | Mon 11/2/09 | Fri 11/13/09 | 40 | 43 | ACI crew |
Aluminium rails installation | 5 days | Mon 11/2/09 | Fri 11/6/09 | 40 | 43 | ACI crew |
Mansory on the stairs | 10 days | Mon 11/16/09 | Fri 11/27/09 | 41,42 | 45 | Souther States Mansory Inc.,Natural Stone Materials [1 tons] |
Post-Construction | 11 days? | Thu 12/31/09 | Thu 1/14/10 | |||
Thorough Clean-up , ACI Punch List Completion and Run Through | 4 days | Thu 12/31/09 | Tue 1/5/10 | 4,17,35,43,15,23,14,28,34 | 46 | Tom Grott,Larry Hawker ,Bridget Brodbeck ,Cleaning supplies[1 units] |
Fire Marshall Inspection | 5 days | Wed 1/6/10 | Tue 1/12/10 | 45,1 | 47 | Bridget Brodbeck |
Project complete | 1 day? | Wed 1/13/10 | Wed 1/13/10 | 46 | 48 | |
Project Review | 1 day | Thu 1/14/10 | Thu 1/14/10 | 47 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started