Question
Amesbury Construction assembles residential homes. It uses a job-costing system with two direct cost categories (direct materials and direct labour) and one indirect cost pool
Amesbury
Construction assembles residential homes. It uses a job-costing system with two direct cost categories (direct materials and direct labour) and one indirect cost pool (assembly support). The allocation base for assembly support costs is direct labour-hours. In December 2018, Amesbury budgets 2019 assembly support costs to be $8,160,000 and 2019 direct labour-hours to be 170,000. At the end of 2019, Anderson is comparing the costs of several jobs that were started and completed in 2019. Information for a couple of jobs follows:
Laguna Model
Mission Model
Construction Period
February-June 2019
May-October 2019
Direct materials
$105,620
$126,522
Direct labour
$34,109
$39,920
Direct labour-hours
860
990
Direct materials and direct labour are paid for on a contract basis. The costs of each are known when direct materials are used or direct labour-hours are worked. The
2019
actual assembly support costs were
$6,232,000,
while the actual direct labour-hours were
164,000.
Required
LOADING...
Requirement 1. Compute the (a) budgeted and (b) actual indirect cost rates. Why do they differ?
Identify the formula to calculate the budgeted indirect cost rate and then calculate the rate. (Round your answers to the nearest whole dollar.)
/ | = | Budgeted indirect cost rate |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started