Question
An 8-associate production crew is deployed on an assembly line as shown below. Assume all associates are equally experienced and skilled and that the line
An 8-associate production crew is deployed on an assembly line as shown below. Assume all associates are equally experienced and skilled and that the line flows continuously without stoppages: Section Associate Takt time (s) # of picks Responsibilities
Section | Associate | Takt time | No of picks | Responisbilities |
1 | A | 6 | 0 | Label and build box |
B | 4 | 2 | Pick ice packs | |
C | 7 | 6 | Pick chilled ingredients | |
D | 4 | 2 | Pick chilled ingredients | |
Box travels on automated conveyor to new section of line | ||||
2 | E | 8 | 5 | Pick non-chilled ingredients |
F | 5 | 3 | Pick non-chilled ingredients | |
G | 3 | 3 | Pick recipe cards | |
H | 2 | 0 | Seal box |
1. As deployed above, how many completed boxes can this crew assemble per hour? Which associate is currently the bottleneck? 2. Put yourself in the shoes of a Line Lead trying to maximize line speed. What changes would you consider to increase the hourly box throughout the line? What speed would these changes result in? 3. Now think of yourself as an Operational Excellence Analyst tasked with running this line as efficiently as possible. This line must assemble 3,800 boxes to ship out every 8 hours. Assuming each associate scheduled must work an 8 hour shift, how would you deploy an ideal crew? How many associates are required to hit the ship out time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started