An activity on a PERT network has an optimistic time of 1 week, a most likely time of 2 weeks, and a pessimistic time of
An activity on a PERT network has an optimistic time of 1 week, a most likely time of 2 weeks, and a pessimistic time of 4 weeks. Find its STANDARD DEVIATION. Group of answer choices 2 weeks 1.5 weeks