An activity on a PERT network has an optimistic time of 4 hours, a most likely time of 6.25 hours, and a pessimistic time of

An activity on a PERT network has an optimistic time of 4 hours, a most likely time of 6.25 hours, and a pessimistic time of 22 hours. Find its STANDARD DEVIATION.

Group of answer choices 5 hours 4 hours 3 hours 4.5 hours 3.5 hours

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Research Methods

Authors: Alan Bryman, Emma Bell

3rd Edition

0199583404, 9780199583409

More Books

Students also viewed these General Management questions

Question

Distinguish between operating mergers and financial mergers.

Answered: 1 week ago