Question

1 Approved Answer

An activity on the project network has a slack time of 0 days. Which of the following is always true? Increasing the activity time by

An activity on the project network has a slack time of 0 days. Which of the following is always true?

Increasing the activity time by 2 days will decrease project duration by 2 days.

Decreasing the activity time by 2 days will increase project duration by 2 days.

Decreasing the activity time by 2 days will decrease project duration by 2 days.

Increasing the activity time by 2 days will increase project duration by 2 days.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Experiencing MIS

Authors: David M Kroenke, Randall J Boyle

6th Edition

0133939146, 9780133939149

More Books

Students also viewed these General Management questions