An agile project's plan shows that it was supposed to have completed 250 story points at a certain point in time but fell short of
An agile project's plan shows that it was supposed to have completed 250 story points at a certain point in time but fell short of that target by 50 story points. What is the project's Schedule Performance Index (at that point in time)? Question 8 options: 0.2 5 1.25 0.8