Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

An airborne warning and control system is being built as part of a large defence project. The project comprises two main sub-systems (a) detection sub-system

image text in transcribed

An airborne warning and control system is being built as part of a large defence project. The project comprises two main sub-systems (a) detection sub-system and (b) guidance subsystem. In implementing the project, the following precedence relationships must be adhered to: 1. Calibration of machines precedes production, independently for each sub-system i.e., (a) Calibration of machine 1 must be done prior to production of detection sub-system. (b) Calibration of machine 2 must be done prior to production of guidance sub-system. 2. Testing of detection sub-system can only be done after production of detection subsystem and testing of electronic controls. 3. Testing of guidance sub-system can only be done after production of guidance subsystem and testing of electronics controls. 4. Projectile testing can be started immediately after calibration of machine 2 is completed. 5. Assembly of detection and guidance sub-systems as well as ground control co-ordination can be started only after the testing of both sub-systems has been completed. 6. Preparation of final test gear involves several complex assemblies and can be initiated at the beginning of the project. However it must be completed before final testing can start. 7. Final testing requires the completion of assembly of detection and guidance subsystems, ground control co-ordination, and projectile testing. The time required to complete the various tasks of the project are given in the table below: TABLE 1: Tasks and Activity Times (a) Identify the immediate predecessor activities for each task in Table 1 and develop a project network. (b) Determine the earliest and latest start and finish times for each activity. Identify the critical activities which if delayed will delay the overall completion time of the project. (c) Which activities should definitely be completed by week 15 if the project is not to be delayed? An airborne warning and control system is being built as part of a large defence project. The project comprises two main sub-systems (a) detection sub-system and (b) guidance subsystem. In implementing the project, the following precedence relationships must be adhered to: 1. Calibration of machines precedes production, independently for each sub-system i.e., (a) Calibration of machine 1 must be done prior to production of detection sub-system. (b) Calibration of machine 2 must be done prior to production of guidance sub-system. 2. Testing of detection sub-system can only be done after production of detection subsystem and testing of electronic controls. 3. Testing of guidance sub-system can only be done after production of guidance subsystem and testing of electronics controls. 4. Projectile testing can be started immediately after calibration of machine 2 is completed. 5. Assembly of detection and guidance sub-systems as well as ground control co-ordination can be started only after the testing of both sub-systems has been completed. 6. Preparation of final test gear involves several complex assemblies and can be initiated at the beginning of the project. However it must be completed before final testing can start. 7. Final testing requires the completion of assembly of detection and guidance subsystems, ground control co-ordination, and projectile testing. The time required to complete the various tasks of the project are given in the table below: TABLE 1: Tasks and Activity Times (a) Identify the immediate predecessor activities for each task in Table 1 and develop a project network. (b) Determine the earliest and latest start and finish times for each activity. Identify the critical activities which if delayed will delay the overall completion time of the project. (c) Which activities should definitely be completed by week 15 if the project is not to be delayed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Financing Financial Instruments And Risk Management

Authors: Frank J Fabozzi, Carmel De Nahlik

1st Edition

9811231494, 9789811231490

More Books

Students also viewed these Finance questions