An analysis has been undertaken by the industrial engineering staff in consultation with the activity managers. The activity listed below can be crashed. Reduce the

image text in transcribed

An analysis has been undertaken by the industrial engineering staff in consultation with the activity managers. The activity listed below can be crashed. Reduce the project duration as much as cost justified by crashing selected activities. Remember, you must crash the whole activity and that the crashing ranking is 1) Critical Path, 2) Lowest Crash Cost, 3) Earliest in the Project

  1. Develop & Issue Computer Hardware RFP

A Subcontractor can assist with the writing of the hardware RFP, such that the activity duration can be reduced from 6 days to 3 days for an added cost of $2,000 to the activity.

  1. Software Documentation The software vendor can reduce the duration of this activity from 8 days to 4 days through the use of additional staffing and overtime, at a cost of $3,500.
  2. Post Systems Manager Position Announcement As per TC policy, the posting period for the new systems manager position can be reduced form 10 days to 3 days by using overnight and electronic mailing of the announcement to all TC locations, and accepting electronic applications. The added cost to the activity would be $3,000
  3. Modify Software The Software vendor can work weekends and overtime to make the required software modifications. The activity time can be reduced from 15 days to 5 days, for an added cost of $5,000 to the activity.
  4. Associate Training By training over the weekend, TC can reduce the training activity time from 5 days to 3 days at an additional activity cost of $7,000 in overtime and expenses. This option may create serious quality problems.
  5. Relocate Systems Manager The new systems manager can be housed at additional expense in a hotel temporarily to reduce relocation time from 10 to 8 days. The added cost to the activity would be $4,000.

7. Construct Building Space The conversion of the building space can be accomplished by a subcontractor, working 24 hours a day, with a reduction in construction time from 6 to 3 days for an added activity cost of $2,000

image text in transcribed

21 829 Write Software Documentation 22 1 30 6 15 21 Modify Software 60 21 21 6 27 Live File Test 21 0 27 27 3 30 Benchmark Test 27 0 30 03 Finalize Sys Specs 30 $ 35 Write User Documentation 30 0 35 3 3 6 Approve Sys Specs 30 6 0 Project Start 0 0 0 355 40 Train Associates 35 0 40 6 6 12 Develop HW RFP 13 7 19 12820 Hardware Bid Period 19 7 27 20 2 22 Issue HW Purchase Order 27 7 29 22 6 28 Install HW & LAN 29 7 35 40 10 50 Conversion & Parallel 40 0 50 63 9 Select Building Space 15 9 18 9 2. 11 Execute Building Space 18 9 20 11 3 14 Design Building 20 9 23 Space 620 Construct Building Space 23 9 29 0 4 Dev Position Announcement 10 14 Post Position Announcement 18 14 7 21 Select Systems Manager 18 4 25 21 10 31 Relocate System Manager 25 4 35 Activity Crashed New Project Duration Added Cost Critical Path Step 0 1 2 w N 1 4 5 6 7 8 Total 21 829 Write Software Documentation 22 1 30 6 15 21 Modify Software 60 21 21 6 27 Live File Test 21 0 27 27 3 30 Benchmark Test 27 0 30 03 Finalize Sys Specs 30 $ 35 Write User Documentation 30 0 35 3 3 6 Approve Sys Specs 30 6 0 Project Start 0 0 0 355 40 Train Associates 35 0 40 6 6 12 Develop HW RFP 13 7 19 12820 Hardware Bid Period 19 7 27 20 2 22 Issue HW Purchase Order 27 7 29 22 6 28 Install HW & LAN 29 7 35 40 10 50 Conversion & Parallel 40 0 50 63 9 Select Building Space 15 9 18 9 2. 11 Execute Building Space 18 9 20 11 3 14 Design Building 20 9 23 Space 620 Construct Building Space 23 9 29 0 4 Dev Position Announcement 10 14 Post Position Announcement 18 14 7 21 Select Systems Manager 18 4 25 21 10 31 Relocate System Manager 25 4 35 Activity Crashed New Project Duration Added Cost Critical Path Step 0 1 2 w N 1 4 5 6 7 8 Total

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Accounting And Finance

Authors: Geoff Black

2nd Edition

0273711628, 978-0273711629

More Books

Students also viewed these Accounting questions