An approach to creating a work breakdown structure for a project that modifies or edits work breakdown structures from similar previous projects is the: Group
An approach to creating a work breakdown structure for a project that modifies or edits work breakdown structures from similar previous projects is the: Group of answer choices top-down approach guideline approach analogy approach bottom-up approach