An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 275 units per day. Here are
An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 275 units per day. Here are the tasks and their performance times:
TASK | PRECEDING TASKS | PERFORMANCE TIME (SECONDS) |
---|---|---|
A | 60 | |
B | 28 | |
C | 20 | |
D | A | 50 |
E | B | 55 |
F | C | 58 |
G | D | 30 |
H | E | 60 |
I | F | 10 |
J | G | 25 |
K | H, I | 67 |
L | J, K | 30 |
d.Assign tasks to workstations using the longest task time.
Note: Leave no cells blank - be certain to enter "0" wherever required.
d. Assign tasks to workstations using the longest task time. Note: Leave no cells blank - be certain to enter "0" wherever required
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started