An assembly line produces 800 products per hour, with a standard deviation of demand during lead time of 100. For every product they make they

An assembly line produces 800 products per hour, with a standard deviation of demand during lead time of 100. For every product they make they use a Kanban system. The lead time from the inventory location to the assemble line is 2 hours. The boxes the product is transported in can carry 200 items and the company uses an alfa factor of 0.1.?

1. What's the number of Kanban cards they need?

2. If they instead want to use a ROP system, what will the ROP be?

3. What service level does the safety stock represent ? (The probability of not having a shortage during one inventory cycle.)


Step by Step Solution

3.46 Rating (162 Votes )

There are 3 Steps involved in it

Step: 1

Average demand d 800 per hr Stdev of lead time dema... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Statistics For The Behavioral Sciences

Authors: Frederick J Gravetter, Larry B. Wallnau

8th Edition

1133956572, 978-1133956570

More Books

Students also viewed these General Management questions

Question

=+c) What summary statistics would you use to describe these data?

Answered: 1 week ago

Question

T F Antidepressants are used only to treat depression. (p. 90)

Answered: 1 week ago

Question

2.10 Evaluate the biopsychosocial perspective on abnormal behavior.

Answered: 1 week ago

Question

T F Anxiety can give you indigestion. (p. 46)

Answered: 1 week ago