An assembly line with 1 7 tasks is to be balanced. The longest task is 2 . 4 minutes, and the total time for all

An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.
a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)
b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the smaller value in the first box and the larger value in the second box.)
c. What is the minimum number of workstations needed if the maximum output rate is to be sought? (Round up your answer to the next whole number.)
d. What cycle time will provide an output rate of 125 units per day? (Round your answer to 1 decimal place.)
e. What output potential will result if the cycle time is (1)9 minutes? (2)15 minutes?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wildlife Ecology Conservation And Management

Authors: John M. Fryxell, Anthony R. E. Sinclair, Graeme Caughley

3rd Edition

1118291077, 978-1118291078

More Books

Students also viewed these General Management questions

Question

a. Did you express your anger verbally? Physically?

Answered: 1 week ago

Question

b. Did you suppress any of your anger? Explain.

Answered: 1 week ago