An assembly line with 17 tasks is to be balanced. The longest task is 2.9 minutes, and the total time for all tasks is 24
An assembly line with 17 tasks is to be balanced. The longest task is 2.9 minutes, and the total time for all tasks is 24 minutes. The line will operate for 476 minutes per day. What is the minimum number of workstations needed if the maximum output rate is to be sought? (Do not round intermediate calculations