Question

1 Approved Answer

An assembly line with 20 activities is to be balanced. The total amount of time to complete all 20 activities is 60 minutes. The longest

An assembly line with 20 activities is to be balanced. The total amount of time to complete all 20 activities is 60 minutes. The longest activity takes 2.1 minutes and the shortest takes 1.0 minute. The line will operate for 420 minutes per day.

What are the maximum and minimum cycle times? Round your answers to one decimal place.

Maximum cycle time: ? minutes

How much daily output will be achieved by each of those cycle times? Round your answers to the nearest whole number.

Daily output achieved by maximum cycle time: ? units/day

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wildlife Ecology And Management

Authors: Eric G. Bolen, William Laughlin Robinson

5th Edition

013066250X, 978-0130662507

More Books

Students also viewed these General Management questions

Question

=+(18.17) [ G(n)fn=F(x)G(x)-["F(t)8(t)dt ROEnEX

Answered: 1 week ago

Question

3. Contrast relational contexts in organizations

Answered: 1 week ago

Question

2. Describe ways in which organizational culture is communicated

Answered: 1 week ago

Question

1. Describe and compare approaches to managing an organization

Answered: 1 week ago