An assembly line with 30 activities is to be balanced. The total amount of time required for all 30 activities is 34 minutes. The line
An assembly line with 30 activities is to be balanced. The total amount of time required for all 30 activities is 34 minutes. The line will operate for 495 minutes per day. Which of the following must be the cycle time to achieve an output rate of 165 units/day?
| |||
| |||
| |||
|