Question

1 Approved Answer

An assembly line with 30 activities is to be balanced. The total amount of time required for all 30 activities is 34 minutes. The line

An assembly line with 30 activities is to be balanced. The total amount of time required for all 30 activities is 34 minutes. The line will operate for 495 minutes per day. Which of the following must be the cycle time to achieve an output rate of 165 units/day?

a. 0.3 minutes
b. 3.0 minutes
c. 0.9 minutes
d. 2.4 minutes

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Elements Of Chemical Reaction Engineering

Authors: H. Fogler

6th Edition

9780135486221

Students also viewed these Accounting questions