An auditor assessed the audit risk for an engagement to be 6%. They determined inherent risk of the engagement to be 80% and the control
An auditor assessed the audit risk for an engagement to be 6%. They determined inherent risk of the engagement to be 80% and the control risk to be 50%. What is the maximum amount of detection risk they are willing to accept in the audit?
(A) 10%
(B) 12%
(C) 15%
(D) 20%