An electrical contractor as a job which should be completed in 100 days. At present, he has 80 men on the job and it is

An electrical contractor as a job which should be completed in 100 days. At present,

he has 80 men on the job and it is estimated that they will finish the work in 130

days. If of the 80 men, 50 are paid P62 a day, 25 at P68 a day, and 5 at P75 a day

and if for each day beyond the original 100 days, the contractor has to pay P250

liquidated damages:

(a) How many more men should the contractor add so he can complete the work

on time?

(b) If the additional men of 5 are paid P68 a day and the rest at P62 a day, would

the contractor save money by employing more men and not paying the fine?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods for Business

Authors: David R. Anderson, Dennis J. Sweeney, Thomas A. Williams, Jeffrey D. Camm, James J. Cochran

13th edition

1285866312, 978-0357685648, 978-1285866314

More Books

Students also viewed these Economics questions

Question

2. How do I perform this role?

Answered: 1 week ago