An electrical contractor as a job which should be completed in 100 days. At present, he has 80 men on the job and it is
An electrical contractor as a job which should be completed in 100 days. At present,
he has 80 men on the job and it is estimated that they will finish the work in 130
days. If of the 80 men, 50 are paid P62 a day, 25 at P68 a day, and 5 at P75 a day
and if for each day beyond the original 100 days, the contractor has to pay P250
liquidated damages:
(a) How many more men should the contractor add so he can complete the work
on time?
(b) If the additional men of 5 are paid P68 a day and the rest at P62 a day, would
the contractor save money by employing more men and not paying the fine?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started