Question

1 Approved Answer

An engineer issued revised foundation plans due to differing site conditions in a five-story office-building project. The foundation design was changed based on the newly

An engineer issued revised foundation plans due to differing site conditions in a five-story office-building project. The foundation design was changed based on the newly identified site conditions. The above variation resulted in a 20 - day delay in the critical path.

Considering the following figures, calculate the total value of variations based on NZS 3910:2013.

image text in transcribed
Previous work items Qty Unit New work items Qty Unit Excavation 30 m3 Excavation 45 m3 Concrete for bases 16 m3 Concrete for bases 28 m3 Formwork 56 ma Formwork 81 m2 Reinforcement 300 kg Reinforcement 850 kg Schedule of rates Item Rate Unit Excavation 20.00 NZD/m3 Concrete for bases 250.00 NZD/m3 Formwork 55.00 NZD/m2 Reinforcement 8.00 NZD/kg

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions