Question

1 Approved Answer

An engineer makes $84,000 per year with benefits and overhead costing and additional $60,000 per year. The companies target profit is 20% and the target

An engineer makes $84,000 per year with benefits and overhead costing and additional

$60,000 per year. The companies target profit is 20% and the target utilization rate is 75%.

What is the fully burdened rate for the engineer? Using the equation attached please.

image text in transcribed

total cost billing rate = x profit multiple capacity x utilization This is the "fully burdened rate

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting The Cornerstone Of Business Decision-making, , (6 Months)

Authors: Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger

7th Edition

1337115924, 9781337115926

More Books

Students also viewed these Accounting questions