An entity started construction on a building for its use on 1 st April 2 0 1 7 and incurred the following costs: $ 0
An entity started construction on a building for its use on st April and incurred the
following costs:
$
Purchase price of land
Stamp Duty
Legal Fees
Site preparation and clearance
Materials
Labour period April to July
Architect's fees
General Overheads
The following information is also relevant:
Material costs were greater than anticipated. On investigation, it was found that materials
costing $ million had been spoiled and therefore wasted and a further $ million was incurred
on materials as a result of faulty designed work.
As a result of these problems, work on the building ceased for a fortnight during October
and it is estimated that approximately $ million of the labour costs relate to this period.
The Building was completed on July and occupied on September You are
required to calculate the cost of building that will be included in tangible non current asset
additions. You are also required to show the carrying amount of the building for the year ended
Dec if the life of the building is estimated to be years under Cost model and under
Revaluation model of the Fair value of the building was estimated to be million as on that
date.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started