An expert estimates Optimistic, Most Likely and Pessimistic durations for a work package. O=2 days, M=6 Days and P=10 days. What are the BETA and
An expert estimates Optimistic, Most Likely and Pessimistic durations for a work package. O=2 days, M=6 Days and P=10 days. What are the BETA and (simpler) Triangular estimates?
1 | 7 days and 5 days |
2 | They are both 6 days |
3 | 6 Days and 4 days |
4 | They are both 5 days |