Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

An expert estimates Optimistic, Most Likely and Pessimistic durations for a work package. O=2 days, M=6 Days and P=10 days. What are the BETA and

An expert estimates Optimistic, Most Likely and Pessimistic durations for a work package. O=2 days, M=6 Days and P=10 days. What are the BETA and (simpler) Triangular estimates?

1

7 days and 5 days

2

They are both 6 days

3

6 Days and 4 days

4

They are both 5 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Enterprise Risk Management

Authors: Rick Nason, Leslie Fleming

1st Edition

1947098365, 978-1947098367

More Books

Students also viewed these General Management questions

Question

How comparable are the groups in causal comparative studies?

Answered: 1 week ago