Question
An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production
An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,200 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza.
Task Immediate Predecessors Task Duration (Seconds)
A none 10
B A 14
C B 20
D B 16
E C,D 12
F E 2
Design this layout using the decision rule of Longest Processing Time (LPT). Which of the following is closest to the efficiency of your design?
a. | 17% | |
b. | 60% | |
c. | 72% | |
d. | 40% | |
e. | 82% |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started