An industrial plant needs to make 100,000 parts per month to meet demand. Each month contains 20 working days, each of which allows for

 

An industrial plant needs to make 100,000 parts per month to meet demand. Each month contains 20 working days, each of which allows for 3 separate 8 hour shifts. (a) If a worker can produce 10 parts/hour, how many workers are needed on each shift? (b) If material costs are $10/part, capital costs are $100,000 and labor costs are $10/hour, what is the multifactor productivity of the plant from part (a)?

Step by Step Solution

3.40 Rating (150 Votes )

There are 3 Steps involved in it

Step: 1

a To produce 100000 parts per month with each worker producing 10 parts per hour you can calculate t... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting Information for Decision-Making and Strategy Execution

Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young

6th Edition

137024975, 978-0137024971

More Books

Students also viewed these General Management questions

Question

What might be included as cash inflows from financial investments?

Answered: 1 week ago

Question

What are the need and importance of training ?

Answered: 1 week ago

Question

What is job rotation ?

Answered: 1 week ago