An M / M /3 system has an arrival rate of 16 customers per hour. Each server has a service rate of 12 customers per
AnM/M/3 system has an arrival rate of 16 customers per hour. Each server has a service rate of 12 customers per hour.
- What is the utilization factor for this system?(Round your answer to 3 decimal places.)
- If all servers are kept busy, how many services will be completed per hour?(Round your answer to the nearest whole number.)