An order for 100 units of Alpha is scheduled to be shipped at the start of week 9. End item Alpha's product structure tree

 

An order for 100 units of Alpha is scheduled to be shipped at the start of week 9. End item Alpha's product structure tree and inventory information are as follows: LT On-Hand Item Alpha Alpha 15 3. 30 H3) K M(2) M 3. 30 10 30 P2) W(2) S(2) B(2) W(4) S(2) 100 5. What is the gross requirement for H to fill this order? 6. What is the net requirement for H to fill this order? 7. When should an order for P be relcased? 8. How many units of P should be ordered? The table used in MRP is as follows: Lead Time Beg. 1 2 Item 3 4 5 6 8 Inv. Gross requirements Scheduled receipts Projected on hand Net requirements Planned-order receipts Planned-order releases

Step by Step Solution

There are 3 Steps involved in it

Step: 1

For Alpha scheduled shipment is start of week 9 lead time 2 weeks So alpha has to be orderd at the beginning of week 7 92 net requirement 100 gross 0 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Document Format ( 2 attachments)

PDF file Icon
635d9f72d31c6_177385.pdf

180 KBs PDF File

Word file Icon
635d9f72d31c6_177385.docx

120 KBs Word File

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Managing Global Supply Chains

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

1st edition

1506302935, 1506302939, 978-1506302935

More Books

Students also viewed these General Management questions

Question

What are four principles of effective post project reviews?

Answered: 1 week ago