An order for 100 units of Alpha is scheduled to be shipped at the start of week 9. End item Alpha's product structure tree
An order for 100 units of Alpha is scheduled to be shipped at the start of week 9. End item Alpha's product structure tree and inventory information are as follows: LT On-Hand Item Alpha Alpha 15 3. 30 H3) K M(2) M 3. 30 10 30 P2) W(2) S(2) B(2) W(4) S(2) 100 5. What is the gross requirement for H to fill this order? 6. What is the net requirement for H to fill this order? 7. When should an order for P be relcased? 8. How many units of P should be ordered? The table used in MRP is as follows: Lead Time Beg. 1 2 Item 3 4 5 6 8 Inv. Gross requirements Scheduled receipts Projected on hand Net requirements Planned-order receipts Planned-order releases
Step by Step Solution
There are 3 Steps involved in it
Step: 1
For Alpha scheduled shipment is start of week 9 lead time 2 weeks So alpha has to be orderd at the beginning of week 7 92 net requirement 100 gross 0 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
635d9f72d31c6_177385.pdf
180 KBs PDF File
635d9f72d31c6_177385.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started