Question
1 Approved Answer
An order for 5 0 of a product is processed on work centers A and B . The setup time on A is 6 0
An order for of a product is processed on work centers A and B The setup time on A is minutes, and run time is minutes per piece. The setup time on B is minutes, and the run time is minutes per piece. Wait time between the two operations is hours. The move time between A and B is minutes. Wait time after operation B is hours, and the move time into stores is hours. Queue at work center A is hours and at B is hours. Calculate the total manufacturing lead time for the order.
Step by Step Solution
There are 3 Steps involved in it
Step: 1