An organization is about to start a new software development project. The assigned Project Manager has already created a resource calendar for facilitating the effective
An organization is about to start a new software development project. The assigned Project Manager has already created a resource calendar for facilitating the effective allocation of personnel and aiding in the estimation of project costs. Resource System Analyst 1 System Analyst 2 Marketing Expert 1 Marketing Expert 2 Hourly Rate ($/h) 30 30 20 20 Week 1 (hours) 40 40 40 40