An organization planned to use $94 of direct materials per unit of output, but it actually used $92 per unit. During this period, the
An organization planned to use $94 of direct materials per unit of output, but it actually used $92 per unit. During this period, the company planned to make 2,520 units, but produced only 2,200 units. The flexible budget amount for direct materials cost is: Multiple Choice $202,400. $206,800. $231,840. $236,880. $51,165.